A Case Study in Learning

During a recent CIBSE CPD, we presented on ‘The Safe Use of Gas in Education’ a question was asked about the need for commissioning when our gas control systems were installed.  The engineer asking the question had experience of our systems, understood they were designed to be simple to install and that with an LCD information was displayed clearly for installation diagnostics and user operation.

We spoke of the need for commissioning as laid out within the standards but also explained that for us at Medem, safety is always our primary concern and that within the gas industry we should never assume systems have been installed correctly no matter how simple they are to install.

There are many positives to commissioning, not just confirmation of correct operation.

For instance where our systems are commissioned by a Medem engineer not only do we ensure the items are installed and operating correctly, double our industry leading 5-year warranty to 10 years, provide a 24-hour telephone support number but importantly we also check to ensure the correct system type is installed.

From the original site design to installation a specification can pass through several revisions, a change of design team, take several months and in some cases years before completion on site. This means that the originally designed use of a room or type of installed appliances may differ from the original concept, so the gas safety panel requirements may also now be different.

Classrooms that have changed from laboratories to home economics rooms, classrooms with brazing equipment or kilns that were not on the designs when the gas controls systems were specified and chosen are just a couple of examples.

Because we develop and manufacture our own products we have designed flexibility within the gas safety systems so that we can enable or disable options during the commissioning to reduce or remove potential handover delays.

Although not every site change is as simple as sliding an option switch.

We recently attended site to commission a system within a boiler room of a school which had gone through a partial refurbishment, the old boilers had been replaced for shiny new and more efficient ones.

Due to its rural location and the site being prone to power cuts of fluctuating lengths the specification included for a Medem SEC-B system, detectors and commissioning. For those that don’t know, the SEC-B is a gas detection and gas pressure proving panel specifically designed to help the site meet parts of Building Bulleting 100: Design for fire safety in schools. Monitoring the boiler room for gas leaks but crucially it can automatically restart the gas supply after a power cut.

Once installed the SEC-B was turned on, a downstream integrity test completed and a signal was provided for the boiler plant to start and within a couple of minutes the heating was on everything was operating correctly.

As you would expect part of the commissioning is to test all operations of the gas control panel, so power was removed imitating a power cut. When power was restored the system automatically started a gas pressure test, normally a routine operation for a boiler room. However the panel began alarming and indicated a test fail condition, there was a drop in downstream pressure being registered!!

Now, fortunately, the boffins at Medem have designed in an easy way of displaying the real-time pressures on the display to confirm exactly what is happening. Another unique Medem design feature based on site feedback and experience.

So within a matter of seconds, gas pressures had been viewed and the pressure was confirmed to be reduced downstream of the valve. Now the puzzling part for all onsite was the gas pipework and appliances had only just been tightness tested.

So after retesting and much head scratching what was the cause of this mystery?

A water heater…

Replacing the water heater had not been part of the refurbishment so it was still the original unit. When the ‘power cut’ was replicated to simulate a momentary loss of power the flame safety device within the water heater didn’t respond fast enough in closing its local solenoid. So when the gas test began at startup it showed as a test fail and the gas valve remained isolated.

Replacing the water heater was not feasible due to budget restraints so the question was, how do we solve a problem like time?

The answer?…A delay!!

Such an annoying thing if waiting for a train or plane but ideal in this instance.

With the ability to write our own software and make use of modern electronics in our designs and not just using relays we were able to reprogram an SEC-B, creating a delay before the auto restart. The flame safety device then had time to operate, the gas pressure test was then performed, integrity confirmed and the gas supply and boiler plant were reset safely reducing the potential for cold classrooms or even damage due to frozen pipework.

We have taken the information gained from the latest standards, listening to design engineers and the end user, from onsite commissioning’s and our own experience and filtered this back into our latest range of control panels.

Adding failsafe valve and relay checking, fire alarm and time delay auto restarts are just some of the new developments making Medem systems continue to be the most reliable, safest and flexible available today.

Car park exceeds expectations

We have recently completed commissioning of a car park and goods delivery store which had a Medem gas monitoring system installed. The system was designed to monitor for Carbon Monoxide (CO) and Nitrogen Dioxide (NO2) with detection of gas at prescribed levels increasing mechanical ventilation over the set minimum.

New standard acquire

As part of a continuing commitment to improving our products and service, we have successfully introduced our ISO 9001 Quality Management System.

We are now fully compliant with ISO 9001:2008 for the design and manufacture of electronic control systems for use within commercial and public sector buildings.
This means we are regularly audited to ensure only the highest standards are met.

isoqar.com

As part of Medem’s continual investment strategy we have recently completed a major upgrade to our production equipment worth over £180,000.

The purchase of a new ‘iineo‘ surface mount pick and place from Europlacer, Ersa wave solder machine, surface mount printer and optical inspection equipment will provide a significant increase to our production capacity and yet maintain the high quality required for producing safety equipment.

View our new machine in action >

Our new brochure ‘creates a stir’

Our new catalogue has arrived which has all the new products.

It includes all the details on our market first ‘multi-proving’ system and new modular gas detection panel.

Please call on +44 (0)161 233 0600 or email sales@medem.co.uk if you’d like to arrange a visit and receive a printed copy or you can download the brochure here.